2020 Miscellaneous Overlays Project

The City’s 2020 Miscellaneous Overlays Project includes pavement resurfacing of roadways throughout the City. Damaged or settled curb and gutter will also be replaced along with minor storm sewer improvements. Construction is anticipated to begin on July 20, 2020 and be completed by August 16, 2020.

For those properties within the project areas, City representatives will share information with door hangers that will be placed on your front door to let you know when construction will start. Also, we will work with you to have your irrigation heads marked if curb will be removed along your property line that may impact your system.

Parking of vehicles will not be permitted within the project areas between the hours of 7 a.m. and 8 p.m.