205th Street Rehabilitation Project and Ipava Avenue Intersection Improvements at Antlers Park

The City of Lakeville is proposing to rehabilitate asphalt pavement on approximately 1.68 miles of 205th Street West in 2023 from Kenrick Avenue to Ipava Avenue along with the addition of a single lane roundabout at the relocated main park access to Antlers Park. This project includes various methods of pavement rehabilitation, partial curb replacement, trail extensions along 205th Street, roundabout construction, storm sewer repairs, as well as watermain replacement and upgrades at various fire hydrants and street valves.

Project Timeline

  • Fall 2022: Preliminary engineering
  • Winter 2022/2023: Final design
  • February 2023: Project advertised for bidding and Bid opening
  • March 2023: Anticipated award of project
  • May/June 2023: Construction begins

Neighborhood Meeting

March 2023 (date TBD)
This meeting will consist of a short presentation where the public will learn about the project, including anticipated improvements and impacts. Following the presentation, attendees will have the opportunity to ask questions and provide feedback to the project team. The date of the neighborhood meeting will be determined and updated shortly; stay tuned for an update on this webpage or a postcard mailed to your house for those within the project vicinity for a finalized date and location.

Trail Extension

As part of the 205th Street Improvement Project, an asphalt trail will be extended along the north side of 205th Street from Jupiter Way (western segment of the loop) through the Juno Trailway Trailhead to 204th Street (western segment of the loop). The extension of the trail through this gap will provide more direct access from the north side of 205th Street to the Juno Trail network around west Lake Marion and better access to an existing pedestrian crosswalk at the Juno Trailway Trailhead, allowing for safer north-south pedestrian crossings on 205th Street.

Roundabout Improvements

The Antlers Park Master Plan includes relocation of the main park access to Ipava Avenue between 201st Street and 202nd Street. To provide a safe, efficient and multi-modal accessible access, intersection improvements are required along Ipava Avenue. The proposed improvements include construction of a single lane roundabout. The roundabout will be constructed along with the 205th Street improvements, and will be completed prior to the completion of the Antlers Park improvements in 2023. 

Helpful Documents

Contact Us

If you have any questions regarding the project, contact Lucas Ritchie, Civil Engineer, at 952-985-4504 or by email